Spitfire Island A452

In 2104 Callan Connect were instructed to carry extensive BT Openreach diversionary works as part of the Spitfire Island/Chester Road Improvement scheme. These works were essential to allow the development of the island as part of major route expansion too junction 5 of the M6.

Works were completed well in advance of the contractual deadline & within the budget restraints set out by our client. This allowed Openreach to carry out their cable diversions earlier than anticipated, allowing other utility contractors to carry out their works an ultimately meaning that the entire scheme of works was completed on time.

Project: Spitfire Island A452

Client: BT

SCOPE OF

WORK

  • Liaising with the main contractor to co-ordinate works over a 7 month period, ensuring that various health, safety and quality standards were maintained
  • Installation six non-standard Openreach manholes up to a depth of 5.5m
  • Installation 750m of multiway duct
  • Installation 16 node chambers
  • Demolishing 3 x existing manhole chambers
  • Foam filling 4 x redundant manhole chambers